Table 10. Investment cost
Price
No Investment Table Detail
(Euro)
It is envisaged as 3% of the total construction
1 Preliminary Work Expenses 4.405
cost.
It is envisaged as 2% of the total construction
2 Engineering and Project Expenses 3.126
cost.
It is the cost required for the excavation of the
area where the facility will be established and
3 Land and Landscaping 2.936
the transportation of the excavation by trucks. It
was determined as 3% of the construction cost.
2
4 Construction Work Expenses 146.840 The total closed area is 800 m .
It is the cost of machinery and equipment and
Main Facility Machinery and
5 124.550 furnishing, the details of which are given in
Equipment Expenses
Table.
The facility will need 1 forklift to transport and
6 Vehicles, General Expenses 20.000
store the products produced by the business.
7 Working Capital Need 25.000 Investment period working capital requirement
Investment Amount 326.857